What is the correct order of steps during planning poker?

A) Each member of the Scrum Team privately chooses the card representing the estimation.

B) The Scrum Product Owner presents the story.

C) The Scrum Team asks questions

D) People with high and low estimates are allowed to explain their estimate.

E) All selections are revealed.

F) Repeat until a consensus is found among all team members.

    Choose one or more of the following:

  • A, B, C, D, E, F
  • B, C, A, E, D, F
  • F, D, B, E, C, A
  • D, C, E, F, B, A
  • E, A, B, D, F, C